It is road construction season in Indiana and Speedway is seeing a lot of it! Here's an update for work happening around town:

Crawfordsville Rd. is still under construction causing backups throughout the town. This project is being completed by the Indianapolis Department of Public Works. They have not provided additional timeline updates to their original estimated October 30th completion date. However, we are hopeful they will be done sooner. We will keep you updated as we know more.

Locally, we have several projects to finish up that were a part of a large grant awarded this spring. Our crew has provided updated timelines for our projects:

🚧 ELAINE STREET 🚧 
- Sidewalks, curbs, and drives should be completed on Elaine by 7/26 
- Dirt work on Elaine should begin on 7/29
- Asphalt for Elaine should begin on or around 8/12

🚧 PARKWOOD DRIVE 🚧 
- Dirt work being completed on the west side of Parkwood should be finished on 7/25 
- Removal of sidewalks, curbs, and drives on the east side of Parkwood should begin on 7/25 
- New sidewalks, curbs, and drives on the east side of Parkwood should begin on 7/26
- Asphalt for Parkwood should begin on or around 8/12

🚧 BUICK DRIVE 🚧 
- (UPDATED) Removal of sidewalks, curbs, and drives on Buick will begin 8/1
- Replacement of sidewalks, curbs, and drives on Buick and Crosley should begin 8/6

Please note, these timelines are dependent upon weather and other unforeseen factors. We hope this helps provide some insight into what's going on around town and allows you to plan ahead for construction. Thank you for your patience as we all work to update and maintain our roads!