Construction Update: August 15, 2019

constructionupdate

Date: 8/15/2019

We have two new updates on our local construction schedule!

1. Milling will begin on Elaine and Parkwood on 8/26 with paving taking place on 8/27. 
2. Milling will begin on Buick, Crosley, and Desoto on 8/27 with paving taking place on 8/28-8/28.

Additionally, we received an update from Wendell Walters during this week's town council meeting in regards to the City of Indianapolis's project on Crawfordsville Rd. Indy DPW has begun replacing the intermediate asphalt on Crawfordsville road after running into bad concrete under the base of the asphalt. There were a lot more repairs than expected and now their team is in catch up mode and trying to complete as much work as possible prior to the Brickyard 400. Their priority right now is to get the concrete work completed and intermediate asphalt down to make the roads drivable. There will be temporary striping and signage to get fans safely in and out of town prior to the race.

------------------------------------------

🚧 ELAINE STREET 🚧 
- Sidewalks, curbs, and drives should be completed on Elaine by 7/26 
- Dirt work on Elaine should begin on 7/29
- (UPDATED) Milling will begin on Elaine on 8/26
- (UPDATED) Paving will begin on Elaine on 8/27

🚧 PARKWOOD DRIVE 🚧 
- Dirt work being completed on the west side of Parkwood should be finished on 7/25 
- Removal of sidewalks, curbs, and drives on the east side of Parkwood should begin on 7/25 
- New sidewalks, curbs, and drives on the east side of Parkwood should begin on 7/26
- (UPDATED) Milling will begin on Parkwood on 8/26
- (UPDATED) Paving will begin on Parkwood on 8/27

🚧 BUICK DRIVE 🚧 
- (UPDATED) Removal of sidewalks, curbs, and drives on Buick will begin 8/1
- (UPDATED) Replacement of sidewalks, curbs, and drives on Buick and Crosley should begin 8/10
- (UPDATED) Milling will begin on Buick on 8/27
- (UPDATED) Paving will begin on Buick on 8/28-8/29

🚧 CROSLEY LANE & DESOTO LANE 🚧 
- (UPDATED) Milling will begin on Crosley & Desoto on 8/27
- (UPDATED) Paving will begin on Crosley & Desoto on 8/28 and 8/29

Please note, these timelines are dependent upon weather and other unforeseen factors. We hope this helps provide some insight into what's going on around town and allows you to plan ahead for construction. Thank you for your patience as we all work to update and maintain our roads!